Solstice

Solstice Renewables Ltd.

August 28, 2014

Ashcombe Solar Farm Planning Deadline Extended

The original target date for the delegated decision on Solstice Renewables' application to construct a 7.5 MW solar PV park on the Ashcombe Estate was August 29th 2014. However I have just checked the Teignbridge District Council planning web site to see if my own objections to the proposal are visible yet. There I discovered a new letter from the applicant's agent which was posted yesterday, and part of which reads as follows:

More on Ashcombe Solar Farm Planning Deadline Extended

Filed under Renewables by